Humble pursues three transportation projects totaling $15.5 million

The City of Humble is undertaking three road projects: widening South Houston Avenue to three lanes with traffic signals and drainage improvements ($10.3 million), repaving Meek and Manning roads with drainage work ($1.7 million), and replacing asphalt with concrete curb and gutter on McDugald Road, Sharon Drive and Carolyn Court while realigning the intersection at Rankin Road and Kingfisher Drive ($3.5 million).

When it happened
As of October 28, 2026
Where
Humble, Texas
First reported by an outlet
Oct 28, 2026 at 8:13 am
Confirmed by
the original record or a trusted outlet
First reported Oct 28, 2026 · added to this site Oct 28, 2026 at 8:30 am

Taxes & money

WhatAmountWho pays
South Houston Avenue widening project cost$10.3 million[1]Not stated
Meek and Manning roads repaving project cost$1.7 million[1]Not stated
McDugald Road, Sharon Drive and Carolyn Court project cost$3.5 million[1]Not stated

The facts

  1. South Houston Avenue will be widened from two to three lanes between Will Clayton Parkway and Atascocita Road, with a new traffic signal system and drainage improvements, with engineering work about 95% complete as of the Humble City Council agenda packet dated Sept. 24, 2026. [1][1]
  2. Meek and Manning roads will be repaved between North Houston Avenue and Townsen Boulevard with drainage improvements; engineering work is about 90% complete and the project is expected to go out for bids in January 2027, according to Humble Public Works Department officials on Oct. 14, 2026. [1][1]
  3. McDugald Road, Sharon Drive and Carolyn Court will have existing asphalt replaced with concrete curb and gutter, and the intersection at Rankin Road and Kingfisher Drive will be realigned; construction is about 95% complete as of the Public Works Department report, with a timeline from August 2025 to January 2027. [1][1]
  4. A change order was added to the McDugald Road, Sharon Drive and Carolyn Court project to provide additional work on Isaacks Road and Sharon Drive; the project was originally expected to be completed in August 2026. [1][1]

Sources

  1. News Not rated See the latest updates on 3 road projects in Humble Community Impact Newspaper · Oct 28, 2026

Written by AI from the sources above, under fixed rules: every fact is cited, claims are kept apart from facts, and dollar figures appear only when a source states them. Mistakes get corrected in public.

Something wrong here? Tell us →

Your email stays with us