Bond watch
What the bonds are building
When voters approve a bond, the government borrows the money and repays it with property taxes for decades. This is where the money is going, project by project, from the governments' own project records.
Harris County bonds (2015 and 2022)
From Harris County Engineering's bond project map: each project paid for by the county's 2015 or 2022 bonds, the proposition it comes from, its phase, its current budget and what has been spent. Read daily. Last read Oct 26.
157 projects, $1.5B in current budgets, $157.9M spent so far.
| Proposition | Projects | Budget / spent |
|---|---|---|
| B - Transportation | 69 6 done | $794.6M $97.6M spent |
| Not stated | 46 6 done | $432.4M $6.9M spent |
| C - Parks & Trails | 34 2 done | $243.2M $43.3M spent |
| A - Public Safety Facilities | 8 | $77.5M $10.2M spent |
Every project
| Project | Where it stands | Budget / spent |
|---|---|---|
| Bayland Park - Design Phase - 2025 24104MF2YQ01 · Precinct 4 · C - Parks & Trails · county record |
Active Study finish 2027-10-19 |
$81.4M $1.5M spent |
| Burnett Bayland Park - Design Phase - 2024 24104MF3HC01 · Precinct 4 · C - Parks & Trails · county record |
Active Warranty finish 2027-05-15 |
$43M $16M spent |
| Subdivision Improvements - Greenwood Forest Subdivision - 2026 261017N38B01 · Precinct 1 · county record |
Active Study finish 2028-12-14 |
$42.6M $0 spent |
| Telge Rd Segment 6 - from 300-ft North of Grant Rd to 690-ft North of SH99 - 2014 15104MF0DN03 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-07-05 |
$36.2M $5.4M spent |
| Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023 24104MF3A201 · Precinct 4 · B - Transportation · county record |
Active Study finish 2031-09-04 |
$33.7M $380.4K spent |
| Grant Road Segment 2 - from Spring Cypress Road to Shaw Road - 2018 19104MF10401 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-10-11 |
$33.2M $1.6M spent |
| Precinct One Infrastructure Revitalization Program - Group B - 2026 26101XRSAC01 · Precinct 1 · county record |
Active Design finish 2029-07-24 |
$31.6M $494.7K spent |
| Roland Road and Related Infrastructure Drainage Improvements - 2018 19103MF14C01 · Precinct 4 · B - Transportation · county record |
Active Design finish 2028-05-11 |
$30.9M $10.4M spent |
| Precinct One Infrastructure Revitalization Program - Group A -2026 26101HKE7B01 · Precinct 1 · county record |
Active Design finish 2029-06-18 |
$30.7M $317K spent |
| Road Improvements - Spears Road - Antoine Dr to COH Limits - 2026 26101VZ4AC01 · Precinct 1 · county record |
Active Study finish 2030-04-05 |
$29.9M $0 spent |
| Road Improvements - Antoine Drive - Beltway 8 to Spears Road - 2026 26035FSQ7B01 · Precinct 1 · county record |
Active Study finish 2030-04-13 |
$29.8M $0 spent |
| Subdivision Drainage Improvements - Creekstone & Silverstone - 2026 26104TV1FF01 · Precinct 4 · county record |
Active Study finish 2027-04-30 |
$28.9M $0 spent |
| Tanner Rd - from W. Sam Houston Pkwy N frontage to 350' east of Gessner Rd - 2022 23103MF2QC01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2030-01-10 |
$28.3M $1.6M spent |
| Peek Road - from Stockdick School Road to Beckendorff Road - 2023 24104MF3A401 · Precinct 4 · B - Transportation · county record |
Active Design finish 2030-04-04 |
$26.8M $1.2M spent |
| Precinct One Infrastructure Revitalization Program - Group C - 2026 2610133R9B01 · Precinct 1 · county record |
Active Design finish 2029-07-08 |
$25.5M $415.4K spent |
| Northpointe Boulevard Segment 1 - from Grant Rd to Shaw Rd - 2019 20104MF1BP01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-06-12 |
$25.2M $1.4M spent |
| Timberlake Estates Subdivision Drainage Improvements - 2018 19103MF17E01 · Precinct 3 · B - Transportation · county record |
On-Hold Design finish 2027-09-20 |
$25M $1.8M spent |
| Castlewood Sections 1 & 2 Subdivision Drainage Improvements - 2023 24208MF3A901 · Precinct 2 · B - Transportation · county record |
Active Design finish 2030-10-05 |
$24.9M $1.6M spent |
| Roadway Design Concept Report - Catalina Area -2025 25104MF3UK01 · Precinct 4 · B - Transportation · county record |
Active Study finish 2027-09-16 |
$24.8M $90.9K spent |
| Road Improvements - Antoine Drive - W Mt Houston to Tomball Parkway - 2026 26101EWW7B01 · Precinct 1 · county record |
Active Study finish 2030-12-21 |
$24.6M $0 spent |
| Cypress North Houston Rd - from Perry Rd to Jones Rd - 2014 15104MF0CD01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2028-06-21 |
$24.1M $5M spent |
| Sylvan Beach Park Phase I - Park Master Plan Design Implementation - 2023 24102MF35001 · Precinct 2 · C - Parks & Trails · county record |
Active Study finish 2031-01-16 |
$23M $1.3M spent |
| Burnett Bayland Park - Phase 1A.1 Landscape - 2024 25104MF3UE01 · Precinct 4 · C - Parks & Trails · county record |
Active Construction finish 2027-11-12 |
$22.4M $15.9M spent |
| Fairmont Parkway - 3- From Underwood Road to Driftwood Drive - 2024 24102MF3KJ01 · Precinct 2 · B - Transportation · county record |
Active Study finish 2032-01-19 |
$22M $562.6K spent |
| Fairmont Parkway - 1 - From Red Bluff to 700' West of Canada Drive - 2024 24102MF3KM01 · Precinct 2 · B - Transportation · county record |
Active Study finish 2032-01-19 |
$21.1M $722.7K spent |
| Fairmont Parkway - 4 - From Driftwood Drive to 14th Street - 2024 24102MF3KH01 · Precinct 2 · B - Transportation · county record |
Active Study finish 2032-01-19 |
$20.6M $679.4K spent |
| Stockdick School Road - from Porter Road to Peek Road - 2023 24104MF3A101 · Precinct 4 · B - Transportation · county record |
Active Study finish 2031-08-01 |
$20.4M $397.8K spent |
| Seamist Drive - W 11 Street to Kury Lane - 2023 24104MF38301 · Precinct 4 · B - Transportation · county record |
Active Design finish 2029-04-02 |
$18M $1.1M spent |
| Treaschwig Rd A (Phase 2) - from west of Cypress Creek to 1,000' east of Birnam Wood Blvd - 2014 23103MF2TA01 · Precinct 3 · B - Transportation · county record |
Active Construction finish 2027-04-26 |
$17.8M $10.6M spent |
| Subdivision Improvements - Inwood North Subdivision - 2026 261015VF9B01 · Precinct 1 · county record |
Active Study finish 2028-07-18 |
$17.7M $0 spent |
| Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014 23103MF2QF01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2028-04-17 |
$17.3M $1.4M spent |
| Fairmont Parkway - 2 - From 700' West of Canada Drive to Underwood Road - 2024 24102MF3KK01 · Precinct 2 · B - Transportation · county record |
Active Study finish 2032-01-19 |
$16.9M $516.6K spent |
| Subdivision Improvements - Gateway Place Subdivision - 2026 26101B8E8B01 · Precinct 1 · county record |
Active Study finish 2030-03-16 |
$16.2M $0 spent |
| Park Improvements - Gene and Loretta Russell Park 1 - 2025 25103MF3RX01 · Precinct 3 · C - Parks & Trails · county record |
Active Study finish 2029-12-10 |
$16.1M $138.1K spent |
| Wortham Estates Subdivision Drainage Improvements - 2018 19103MF15701 · Precinct 3 · B - Transportation · county record |
Active Warranty finish 2027-04-11 |
$15.7M $15.4M spent |
| Grant Road Segment 4 - from Cypress Rose Hill Road to Telge Road - 2018 20104MF1BM01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2028-05-02 |
$15.5M $1.9M spent |
| Subdivision Improvements - Inverness Forest Subdivision - 2026 261011B49B01 · Precinct 1 · county record |
Active Study finish 2028-07-18 |
$15.3M $0 spent |
| 2316 Atascocita Road - HCSO Precision Driving Course - Prop A 24035MF3J901 · Precinct 3 · A - Public Safety Facilities · county record |
Active Design finish 2028-03-19 |
$15.2M $950K spent |
| 13103 FM 1960 -HCSO Patrol District 5 - Prop A 24540MF3ES01 · Precinct 3 · A - Public Safety Facilities · county record |
Active Design finish 2029-01-10 |
$15.2M $4.2M spent |
| Hufsmith-Kohrville Road Segment 4 - from 500' north of Holderreith Road to Mahaffey Road - 2015 15104M23NP04 · Precinct 3 · B - Transportation · county record |
Active Study finish 2034-03-29 |
$14.8M $720.2K spent |
| Boudreaux Road Segment 3 - from Old Boudreaux Road to 300' west of Hufsmith-Kohrville Road - 2019 20104MF1C401 · Precinct 3 · B - Transportation · county record |
Active Design finish 2032-01-11 |
$14.5M $1.5M spent |
| 2316 Atascocita Rd - HCSO - Training Academy Expansion - Prop A 24035MF36S01 · Precinct 3 · A - Public Safety Facilities · county record |
Active Design finish 2029-05-22 |
$14M $643.7K spent |
| North Eldridge Parkway - from Spring Cypress Road to Gregson Road - 2015 15104MF0D701 · Precinct 3 · B - Transportation · county record |
Active Bid finish 2029-12-12 |
$13.6M $3.1M spent |
| Subdivision Drainage Improvements - Altamira - 2026 26104DR9JJ01 · Precinct 4 · county record |
Active Study finish 2027-09-29 |
$13.3M $0 spent |
| Road Improvements - Garth Rd 1 FM 1942 to South of Sterling Summer Dr - 2024 24103MF3G901 · Precinct 3 · B - Transportation · county record |
Active Study finish 2032-04-16 |
$13.3M $219.1K spent |
| Will Clayton Pkwy Segment 1 - from 2,700-ft West of South Houston Ave to 1,370-ft East of Wilson Rd - 2022 23103MF2WB01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2027-08-06 |
$13M $667K spent |
| Porter Rd - Clay Rd to Stockdick School Rd - 2023 24104MF3A301 · Precinct 4 · B - Transportation · county record |
Active Design finish 2030-10-31 |
$12.9M $344.6K spent |
| Roadway Maintenance - Asphalt Rehabilitation Package - 2 - 2026 25103MF3PK01 · Precinct 3 · B - Transportation · county record |
Active Bid finish 2028-11-06 |
$12.9M $0 spent |
| Road Improvements - Antoine Drive - Tomball Parkway to Beltway 8 - 2026 26101C487B01 · Precinct 1 · county record |
Active Study finish 2030-06-15 |
$12.9M $0 spent |
| Subdivision Drainage Improvements - Settlers Village - 2026 26104PH7TT01 · Precinct 4 · county record |
Active Study finish 2027-09-30 |
$12.6M $0 spent |
| 2316 Atascocita - HCSO - New Active Shooter Training Facility - Prop A 24035MF36U01 · Precinct 3 · A - Public Safety Facilities · county record |
Active Design finish 2029-05-22 |
$12.6M $672.5K spent |
| Hike and Bike Trail - SCG - Gosling Road to Dr. Ann Snyder Way - 2022 22104MF03R01 · Precinct 3 · B - Transportation · county record |
Active Study finish 2027-11-09 |
$12.3M $566.8K spent |
| Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019 20104MF1C801 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-04-04 |
$12.1M $627.8K spent |
| Subdivision Drainage Improvements - Amhurst Section 2 - 2026 26104YG0UU01 · Precinct 4 · county record |
Active Study finish 2027-10-22 |
$11.7M $0 spent |
| Subdivision Improvements - Fauna Estates Subdivision - 2026 26101D027B01 · Precinct 1 · county record |
Active Study finish 2030-03-13 |
$11.6M $0 spent |
| Subdivision Improvements - Sheldon Woods Subdivision - 2026 26101U3ABC01 · Precinct 1 · county record |
Active Study finish 2028-07-18 |
$11.3M $0 spent |
| Road Improvements - Garth Rd 2 South of Sterling Summer Dr to Ashbel Cove Dr - 2024 24103MF3GA01 · Precinct 3 · B - Transportation · county record |
Active Study finish 2032-04-14 |
$11.3M $497.5K spent |
| Holderrieth Rd Segment 3 - from Hufsmith-Kohrville Rd to Sir Alex Dr - 2017 18104MF0RA01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2030-11-07 |
$11.1M $2.3M spent |
| Boudreaux Road Segment 4 - from 200' east of Hufsmith-Kohrville Road to 700' south of SH-99 - 2022 23103MF2P601 · Precinct 3 · B - Transportation · county record |
Active Design finish 2032-08-04 |
$10.9M $336.8K spent |
| Hufsmith-Kohrville Road Segment 3B - from 400' north of Boudreaux Road to 600' north of Holderrieth Road - 2015 23103MF2Q701 · Precinct 3 · B - Transportation · county record |
Active Design finish 2032-02-10 |
$10.4M $241.5K spent |
| Mueschke 9; 500' north of Draper Road to approximately 1000' north of FM 2920 171033020712 · Precinct 4 · B - Transportation · county record |
Active Design finish 2029-06-13 |
$10.2M $2.6M spent |
| University Asia Town Multimodal Path - 2024 24104MF3BJ01 · Precinct 4 · B - Transportation · county record |
Active Initiation finish 2028-12-16 |
$10.2M $166.5K spent |
| Roadway Maintenance - Asphalt Rehabilitation Package - 1 - 2026 25103MF3PJ01 · Precinct 3 · B - Transportation · county record |
Active Bid finish 2028-08-14 |
$9.1M $482.3K spent |
| 1731 Hugh Road - HCSO Swift Water Training Facility - Prop A 23540MF2X501 · Precinct 1 · A - Public Safety Facilities · county record |
Active Design finish 2028-12-20 |
$9.1M $2.9M spent |
| Grant Road Segment 3 - from Telge Rd to Shaw Rd - 2018 19104MF10501 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-03-12 |
$9M $811.7K spent |
| West Rayford Rd Segment 1 - from Kuykendahl Rd to 400' east of W Augusta Pines Pkwy - 2019 20104MF1BT01 · Precinct 3 · B - Transportation · county record |
Active Study finish 2027-06-04 |
$8.9M $740.1K spent |
| South Diamondhead Blvd - from 500-ft West of Sea Palms Dr. to West of Boom Dr. - 2022 23103MF2QZ01 · Precinct 3 · B - Transportation · county record |
Active Study finish 2031-06-27 |
$8.9M $358.9K spent |
| Subdivision Improvements - Fall Creek Subdivision - 2026 26101GOK7B01 · Precinct 1 · county record |
Active Study finish 2028-10-18 |
$8.2M $0 spent |
| 310 Fisher Road - HCSO - Vehicle Crime Processing Facility Expansion - Prop A 24540MF36801 · Precinct 3 · A - Public Safety Facilities · county record |
Active Design finish 2028-06-30 |
$8.1M $578.3K spent |
| Road Improvements - Miller Road 1 - Miller Road 3 to Sheldon - 2026 261019FR8B01 · Precinct 1 · county record |
Active Design finish 2030-07-30 |
$8M $0 spent |
| Corridor Study - Mason Road - 2025 25104MF3WR01 · Precinct 4 · B - Transportation · county record |
Active Planning finish 2027-02-03 |
$7.8M $0 spent |
| 1896 Tidwell (Veterans Memorial Park) - Design, Phase 1 - 2023 24102MF34K01 · Precinct 2 · C - Parks & Trails · county record |
Active Design finish 2029-11-05 |
$7.5M $30K spent |
| Memorial Parkway Subdivision Drainage Improvements - 2018 19103MF14E01 · Precinct 4 · B - Transportation · county record |
Active Design finish 2029-01-18 |
$7.3M $950.7K spent |
| Subdivision Improvements - Shadowlake Estates Subdivision - 2026 26101YNMAC01 · Precinct 1 · county record |
Active Study finish 2028-07-18 |
$7.2M $0 spent |
| Subdivision Drainage Improvements - Nottingham Country - 2026 26104OK2QQ01 · Precinct 4 · county record |
Active Study finish 2028-03-03 |
$7.1M $0 spent |
| Edgewater Park - General Improvement Plan (Phase 2) - 2022 23103MF2VZ01 · Precinct 3 · C - Parks & Trails · county record |
Active Design finish 2028-05-16 |
$6.6M $1M spent |
| Park - Agnes Moffitt - Baseball Facility - 2025 25103MF3RW01 · Precinct 3 · C - Parks & Trails · county record |
Active Study finish 2027-12-21 |
$6.3M $103.5K spent |
| North Eldridge Parkway - from South of Pine Drive to South of Lakewood Meadow Drive - 2021 22103N306630001 · Precinct 3 · B - Transportation · county record |
Active Construction finish 2027-05-15 |
$6.2M $1.4M spent |
| Subdivision Drainage Improvements - Lakeville - 2026 26104ZD5XX01 · Precinct 4 · county record |
Active Study finish 2027-05-31 |
$5.9M $0 spent |
| Hike and Bike Trail - Faulkey Gully - K142-00-00 - 2022 23103MF2W701 · Precinct 3 · B - Transportation · county record |
Active Construction finish 2029-03-07 |
$5.8M $2.7M spent |
| Challenger 7 Imp 20101MF1F101 · Precinct 2 · C - Parks & Trails · county record |
Active Warranty finish 2027-07-02 |
$5.5M $5.2M spent |
| Subdivision Improvements - Sheldon Park Subdivision - 2026 26101WVYAC01 · Precinct 1 · county record |
Active Study finish 2029-09-06 |
$5.3M $0 spent |
| Detention Basin Enhancement Program - Goforth - 2021 21103N306330001 · Precinct 3 · B - Transportation · county record |
Active Warranty finish 2027-03-20 |
$5.3M $5M spent |
| Asphalt Reconstruction Project - Fuqua St.: Furman Rd. to Cullen Blvd. - 2022 22101MF2HR01 · Precinct 1 · B - Transportation · county record |
Active Bid finish 2028-07-15 |
$5.1M $268.3K spent |
| Birnam Wood Blvd Segment 1 - from 450' north of Hickorygate Dr to south of J109-01-01 - 2019 20104MF1BG01 · Precinct 3 · B - Transportation · county record |
Active Bid finish 2028-12-29 |
$5M $632.5K spent |
| 15530 Huffmeister Road (Cypress Camp) - Expansion - 2024 24103MF3EX01 · Precinct 3 · B - Transportation · county record |
On-Hold Planning finish 2028-08-30 |
$4.6M $102K spent |
| Hike and Bike Trail - Russ Poppe Park to Cypress Park - 2025 25103MF3VG01 · Precinct 3 · C - Parks & Trails · county record |
Active Study finish 2029-09-16 |
$4.2M $173.9K spent |
| Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024 25103MF3MT01 · Precinct 3 · B - Transportation · county record |
Active Warranty finish 2027-06-24 |
$4.2M $2.3M spent |
| Site Improvement - Barrett Community Recreational Facility - 2025 25103MF3UJ01 · Precinct 3 · C - Parks & Trails · county record |
Active Planning finish 2030-06-12 |
$4M $59.8K spent |
| Connectivity Project - Bane Park - 2024 24101MF3G301 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-11-22 |
$3.7M $34.3K spent |
| 2316 Atascocita Road - HCSO Firearms Complex Renovations - Prop A 24103MF3JA01 · Precinct 3 · A - Public Safety Facilities · county record |
Active Bid finish 2028-04-10 |
$3.3M $322.7K spent |
| Precinct 1 Facility Improvements - 2700 El Camino Street parking- 2025 25101MF3S501 · Precinct 1 · B - Transportation · county record |
Active Construction finish 2028-06-29 |
$3.2M $317.7K spent |
| Subdivision Reconstruction - Patiowoods - 2024 24208MF3FA01 · Precinct 3 · B - Transportation · county record |
Active Design finish 2029-03-12 |
$3.2M $379.3K spent |
| Subdivision Improvements - Urban Acres Subdivision - 2026 261010FAAC01 · Precinct 1 · county record |
Active Study finish 2028-07-18 |
$3.1M $0 spent |
| John R. Harris Park Phase I - Park Master Plan Design Implementation - 2023 24102MF34G01 · Precinct 2 · C - Parks & Trails · county record |
Active Study finish 2031-10-30 |
$3M $363.2K spent |
| Hike and Bike Trail - Tom Bass Park - 2025 25101MF40201 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-10-02 |
$3M $0 spent |
| Feasibility Study - Bridgeland Center Point Trail - 2025 25104MF3SM01 · Precinct 4 · C - Parks & Trails · county record |
Active Study finish 2027-02-11 |
$2.9M $35.8K spent |
| Subdivision Drainage Improvements - Lakeshore - 2024 24103MF3HD01 · Precinct 3 · B - Transportation · county record |
Active Construction finish 2027-12-06 |
$2.6M $403.3K spent |
| Sidewalk - South Mason from Kingsland Blvd to County Line - 2023 24104MF38501 · Precinct 4 · B - Transportation · county record |
Active Construction finish 2028-03-07 |
$2.6M $317.6K spent |
| Wastewater Connection to Pearland - Tom Bass 1 - 2026 26101LT7HH01 · Precinct 1 · C - Parks & Trails · county record |
Active Scoping finish 2029-06-01 |
$2.6M $0 spent |
| Drainage Improvements Program Manager - Precinct 4 - 2025 25104MF3XU01 · Precinct 4 · county record |
Active Scoping finish 2030-01-15 |
$2.5M $0 spent |
| Sidewalk - Energy Corridor and MultiModal Connectivity - Precinct 4 - 2023 24104MF38Q01 · Precinct 4 · B - Transportation · county record |
Active Study finish 2030-02-07 |
$2.4M $440.7K spent |
| Park Various Locations - Restroom Improvements Phase 2 - 2024 24103MF3HG01 · Precinct 3 · C - Parks & Trails · county record |
Active Construction finish 2028-09-06 |
$2.2M $1.1M spent |
| Subdivision Reconstruction - Mobile Homes Parkland - 2024 24208MF3FC01 · Precinct 3 · B - Transportation · county record |
Active Study finish 2027-12-20 |
$2.1M $296.6K spent |
| Subdivision Drainage Improvements - West Memorial - 2026 26104IC8YY01 · Precinct 4 · county record |
Active Study finish 2027-10-20 |
$1.9M $70.8K spent |
| Subdivision Drainage Improvements - Sommerall - 2026 26104EO4MM01 · Precinct 4 · county record |
Active Study finish 2027-08-17 |
$1.9M $0 spent |
| Drainage Improvements - Huffman Cleveland Road 2024 24103MF3G801 · Precinct 3 · B - Transportation · county record |
Active Study finish 2028-01-19 |
$1.9M $194.1K spent |
| Traffic Signal - City of Piney Point Phase 1 - 2022 23103MF2V801 · Precinct 3 · B - Transportation · county record |
Active Construction finish 2028-04-25 |
$1.8M $263.3K spent |
| Subdivision Drainage Improvements - Mission Bend - 2026 26104JZ3BB01 · Precinct 4 · county record |
Active Study finish 2027-08-17 |
$1.8M $0 spent |
| Geotechnical Investigation - Precinct 1 Infrastructure Revitalization Program - Packages 2-6 - 2026 2610135JXB01 · Precinct 1 · B - Transportation · county record |
Active Study finish 2026-11-23 |
$1.4M $0 spent |
| Lindsay Lyons Park - Parking Lot Expansion - 2023 24103MF38401 · Precinct 3 · C - Parks & Trails · county record |
On-Hold Construction finish 2027-03-01 |
$1.2M $0 spent |
| Traffic Signals - Morton Ranch at Waterstone Falls Drive & Kieth Harrow Boulevard at Westfield Village Drive- FY22-23 24035MF35J01 · Precinct 4 · county record |
Active Design finish 2027-12-06 |
$1.2M $105.4K spent |
| Corridor Study - Clinton Drive - 2024 24102MF3K301 · Precinct 2 · B - Transportation · county record |
Active Planning finish 2027-01-29 |
$1.2M $95.9K spent |
| Parking Lot - Lindsay-Lyons Park and Sports Complex - 2025 26103KW2EE01 · Precinct 3 · C - Parks & Trails · county record |
Active Study finish 2029-02-09 |
$1.1M $48K spent |
| Traffic Signal - Woodforest Boulevard at Barbara Mae Boulevard and Woodforest Boulevard at Dell Dale 23102MF2QX01 · Precinct 2 · county record |
Active Design finish 2028-07-13 |
$1.1M $280K spent |
| Traffic Signal Improvement - Cypresswood Dr at Purple Wisteria Ln. FY23-24 24035MF37H01 · Precinct 3 · county record |
Active Warranty finish 2027-04-14 |
$1M $640.7K spent |
| Subdivision Drainage Improvements - Villages of Bear Creek - 2026 26104US6II01 · Precinct 4 · county record |
Active Study finish 2027-06-17 |
$985.4K $0 spent |
| Subdivision Improvements - Arcadian Gardens Phase 1 - 2024 24103MF3E801 · Precinct 3 · B - Transportation · county record |
Active Study finish 2029-12-04 |
$925.5K $449K spent |
| Sidewalk - Ella Boulevard / Falvel Road - 2022 23103MF2UF01 · Precinct 3 · B - Transportation · county record |
Active Warranty finish 2026-01-07 |
$907.3K $107.1K spent |
| Traffic Signal - Blackhawk Boulevard and Southbluff Boulevard 23102MF2QV01 · Precinct 2 · county record |
Active Warranty finish 2027-03-09 |
$877.7K $617.2K spent |
| Traffic Signal - Aldine Westfield Rd. at W W Thorne Dr. - 2022 23101MF2S701 · Precinct 1 · county record |
Active Warranty finish 2026-06-24 |
$877.6K $611.2K spent |
| Boyce Dorian Park - Playground Upgrades - 2023 24101MF3EM01 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-08-30 |
$851.6K $0 spent |
| Traffic Signal and Intersection Improvements - Peek Road at Elyson Falls Drive - 2022 23104MF2TR01 · Precinct 4 · county record |
Active Construction finish 2027-12-09 |
$843.1K $208K spent |
| Traffic Signal Improvement - Barren Springs Dr at Ella Blvd - FY23-24 24035MF37501 · Precinct 1 · county record |
Active Construction finish 2027-12-05 |
$829.2K $269.5K spent |
| Sylvan Beach Pavilion - Structural Repairs - 2026 260352AMRB01 · Precinct 2 · C - Parks & Trails · county record |
Active Construction finish 2026-10-30 |
$826.4K $163.8K spent |
| LED Lighting Upgrades for Fields 1 & 2 - Bane Park Ballfield - 2026 26035OUZTB01 · Precinct 1 · C - Parks & Trails · county record |
Active Planning finish 2028-11-14 |
$787.4K $7K spent |
| Traffic Signal - Imperial Valley Dr. at Doubletree Glen Dr. - 2023 23101MF2XP01 · Precinct 1 · county record |
Active Warranty finish 2026-11-13 |
$702.8K $645.6K spent |
| Traffic Signal - Gosling Road at Hampton Pointe Blvd- FY22-23 24035MF35E01 · Precinct 3 · county record |
Active Warranty finish 2027-01-29 |
$696.1K $648.8K spent |
| Traffic Signal - Clay & Westfield Village Dr. FY22-23 24035MF37M01 · Precinct 4 · county record |
Active Construction finish 2027-10-01 |
$689.9K $335.3K spent |
| Traffic Signal - Beechnut Street at Beckford Drive - FY22-23 24035MF35K01 · Precinct 4 · county record |
Active Design finish 2028-05-26 |
$663.2K $84.9K spent |
| Traffic Signal - Antoine Drive at Breen Drive - FY23-26 24035MF39K01 · Precinct 1 · county record |
Active Design finish 2028-02-07 |
$650K $309.3K spent |
| Traffic Signal - Bammel North Houston Rd at Misty Valley Dr -FY23-24 24035MF39P01 · Precinct 1 · county record |
Active Study finish 2027-09-10 |
$650K $90.1K spent |
| Corridor Study - Reimagine Hopper Rd - 2024 24102MF3JX01 · Precinct 2 · B - Transportation · county record |
Active Planning finish 2026-06-23 |
$628.9K $431.1K spent |
| Traffic Signal - Kuykendahl Rd at Cypressdale Dr - FY22-23 24035MF35D01 · Precinct 3 · county record |
Active Design finish 2026-12-07 |
$600K $267K spent |
| Traffic Signal Improvement - Gessner Rd at Twelve Lakes - FY23-24 24035MF37P01 · Precinct 3 · county record |
Active Design finish 2027-07-09 |
$584.7K $44.4K spent |
| Traffic Signal - Clinton Drive at Galena Manor Drive 23102MF2QW01 · Precinct 2 · county record |
Active Warranty finish 2026-05-21 |
$454.6K $409.6K spent |
| Pedestrian Improvements - Cypress Creek Greenway Loop 2B - 2024 24103MF3FJ01 · Precinct 3 · C - Parks & Trails · county record |
Active Construction finish 2027-05-31 |
$340K $0 spent |
| Park Improvements - Tom Bass I - Gazebo and Boardwalk - 2026 26101XP7HN01 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-09-29 |
$303.1K $38.9K spent |
| Lift Station Wet Well Rehabilitation - Tom Bass and Adair Parks - 2024 25101MF3Q601 · Precinct 1 · B - Transportation · county record |
Active Warranty finish 2026-09-15 |
$282.2K $278K spent |
| Hike and Bike Trail - Russ Poppe Park to Cypress Park - Phase II- 2026 25103MF3VG02 · Precinct 3 · C - Parks & Trails · county record |
Active Construction finish 2028-09-21 |
$184.7K $0 spent |
| Sidewalk - Royalwood Drive - 2024 25102MF3NS01 · Precinct 2 · B - Transportation · county record |
Active Warranty finish 2027-03-11 |
$184.3K $178.2K spent |
| Bridge Repair - Ella Blvd Over Seals Gully, Precinct 3 24103MF34001 · Precinct 3 · B - Transportation · county record |
Active Design finish 2028-08-04 |
$160K $11.3K spent |
| Tom Bass I Park - Bicycle Traffic Garden Improvements - 2024 24101MF3GQ01 · Precinct 1 · C - Parks & Trails · county record |
On-Hold Design finish 2027-07-16 |
$157K $0 spent |
| Park Improvements - Ann and J. Kent Friedman Park - 2025 26101MF40001 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-07-10 |
$75K $0 spent |
| Utility Improvements - Jones Road Park - 2026 26103DR3JJ01 · Precinct 3 · C - Parks & Trails · county record |
Active Design finish 2026-12-07 |
$20K $3.8K spent |
| Cutten Rd - from south of Bavaria Dr to Cossey Rd - Phase II - 2026 20104MF1C802 · Precinct 3 · B - Transportation · county record |
Active Design finish 2028-02-04 |
$0 spent |
| Precinct 1 Signage, Plaques, Murals, and Site Furnishings - 2026 26101435KB01 · Precinct 1 · C - Parks & Trails · county record |
Active Initiation finish 2028-10-10 |
$0 spent |
| Precinct 1 Parks Signage - Phase 2 - 2026 261016VTKB01 · Precinct 1 · C - Parks & Trails · county record |
Active Initiation finish 2028-10-09 |
$0 spent |
| Skatepark Improvements - Gene Green Park - 2026 26101BA7VB01 · Precinct 1 · C - Parks & Trails · county record |
Active Initiation finish 2028-11-20 |
$0 spent |
| Basketball Court Improvements - Gene Green Park - 2026 26101C60VB01 · Precinct 1 · C - Parks & Trails · county record |
Active Initiation finish 2028-11-09 |
$0 spent |
| Tennis Court Renovation and Basketball Court - Christia Adair Park - 2026 26101FUIVB01 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-11-16 |
$0 spent |
| Road Connection - El Franco Lee Park - 2026 26101GHCED01 · Precinct 1 · A - Public Safety Facilities · county record |
Active Planning finish 2026-09-03 |
$0 spent |
| Study - Blueridge Park Improvements - 2026 26101GMSJC01 · Precinct 1 · county record |
Active Study finish 2029-01-04 |
$0 spent |
| Oak Tree Deck - Christia Adair Park - 2026 26101GQCVB01 · Precinct 1 · C - Parks & Trails · county record |
Active Design finish 2028-11-16 |
$0 spent |
| Bridge Repairs - BRINSAP Package 1 - 2027 261030AU4C01 · Precinct 3 · B - Transportation · county record |
Active Scoping finish 2028-04-09 |
$0 spent |
| Roadway Maintenance - Residential Asphalt Package Crosby - 2027 26103YI64C01 · Precinct 3 · B - Transportation · county record |
Active Planning finish 2028-04-09 |
$0 spent |
| Roadway Maintenance - Asphalt Package Cypress North Houston - 2027 26103ZE04C01 · Precinct 3 · B - Transportation · county record |
Active Scoping finish 2026-08-14 |
$0 spent |
Sources
- Harris County Engineering Department, bond project map (CIPBondMapping)
- Harris County Flood Control District, 2018 Bond Program project table (posted by ReduceFlooding.com, from Commissioner Ramsey's office; the newest quarter is found automatically) · HCFCD 2018 Bond Program
- City of Houston, Capital Improvement Plan projects by council district