Bond watch
What the bonds are building
When voters approve a bond, the government borrows the money and repays it with property taxes for decades. This is where the money is going, project by project, from the governments' own project records.
Harris County bonds (2015 and 2022)
From Harris County Engineering's bond project map: each project paid for by the county's 2015 or 2022 bonds, the proposition it comes from, its phase, its current budget and what has been spent. Read daily. Last read Oct 26.
157 projects, $1.5B in current budgets, $157.9M spent so far.
| Proposition | Projects | Budget / spent |
|---|---|---|
| B - Transportation | 69 6 done | $794.6M $97.6M spent |
| Not stated | 46 6 done | $432.4M $6.9M spent |
| C - Parks & Trails | 34 2 done | $243.2M $43.3M spent |
| A - Public Safety Facilities | 8 | $77.5M $10.2M spent |
B - Transportation
| Project | Where it stands | Budget / spent |
|---|---|---|
| Telge Rd Segment 6 - from 300-ft North of Grant Rd to 690-ft North of SH99 - 2014 15104MF0DN03 · Precinct 3 · county record |
Active Design finish 2029-07-05 |
$36.2M $5.4M spent |
| Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023 24104MF3A201 · Precinct 4 · county record |
Active Study finish 2031-09-04 |
$33.7M $380.4K spent |
| Grant Road Segment 2 - from Spring Cypress Road to Shaw Road - 2018 19104MF10401 · Precinct 3 · county record |
Active Design finish 2029-10-11 |
$33.2M $1.6M spent |
| Roland Road and Related Infrastructure Drainage Improvements - 2018 19103MF14C01 · Precinct 4 · county record |
Active Design finish 2028-05-11 |
$30.9M $10.4M spent |
| Tanner Rd - from W. Sam Houston Pkwy N frontage to 350' east of Gessner Rd - 2022 23103MF2QC01 · Precinct 3 · county record |
Active Design finish 2030-01-10 |
$28.3M $1.6M spent |
| Peek Road - from Stockdick School Road to Beckendorff Road - 2023 24104MF3A401 · Precinct 4 · county record |
Active Design finish 2030-04-04 |
$26.8M $1.2M spent |
| Northpointe Boulevard Segment 1 - from Grant Rd to Shaw Rd - 2019 20104MF1BP01 · Precinct 3 · county record |
Active Design finish 2029-06-12 |
$25.2M $1.4M spent |
| Timberlake Estates Subdivision Drainage Improvements - 2018 19103MF17E01 · Precinct 3 · county record |
On-Hold Design finish 2027-09-20 |
$25M $1.8M spent |
| Castlewood Sections 1 & 2 Subdivision Drainage Improvements - 2023 24208MF3A901 · Precinct 2 · county record |
Active Design finish 2030-10-05 |
$24.9M $1.6M spent |
| Roadway Design Concept Report - Catalina Area -2025 25104MF3UK01 · Precinct 4 · county record |
Active Study finish 2027-09-16 |
$24.8M $90.9K spent |
| Cypress North Houston Rd - from Perry Rd to Jones Rd - 2014 15104MF0CD01 · Precinct 3 · county record |
Active Design finish 2028-06-21 |
$24.1M $5M spent |
| Fairmont Parkway - 3- From Underwood Road to Driftwood Drive - 2024 24102MF3KJ01 · Precinct 2 · county record |
Active Study finish 2032-01-19 |
$22M $562.6K spent |
| Fairmont Parkway - 1 - From Red Bluff to 700' West of Canada Drive - 2024 24102MF3KM01 · Precinct 2 · county record |
Active Study finish 2032-01-19 |
$21.1M $722.7K spent |
| Fairmont Parkway - 4 - From Driftwood Drive to 14th Street - 2024 24102MF3KH01 · Precinct 2 · county record |
Active Study finish 2032-01-19 |
$20.6M $679.4K spent |
| Stockdick School Road - from Porter Road to Peek Road - 2023 24104MF3A101 · Precinct 4 · county record |
Active Study finish 2031-08-01 |
$20.4M $397.8K spent |
| Seamist Drive - W 11 Street to Kury Lane - 2023 24104MF38301 · Precinct 4 · county record |
Active Design finish 2029-04-02 |
$18M $1.1M spent |
| Treaschwig Rd A (Phase 2) - from west of Cypress Creek to 1,000' east of Birnam Wood Blvd - 2014 23103MF2TA01 · Precinct 3 · county record |
Active Construction finish 2027-04-26 |
$17.8M $10.6M spent |
| Telge Rd Segment 5 - from 1,780-ft North of Telge Ranch Rd to 300-ft North of Grant Rd - 2014 23103MF2QF01 · Precinct 3 · county record |
Active Design finish 2028-04-17 |
$17.3M $1.4M spent |
| Fairmont Parkway - 2 - From 700' West of Canada Drive to Underwood Road - 2024 24102MF3KK01 · Precinct 2 · county record |
Active Study finish 2032-01-19 |
$16.9M $516.6K spent |
| Wortham Estates Subdivision Drainage Improvements - 2018 19103MF15701 · Precinct 3 · county record |
Active Warranty finish 2027-04-11 |
$15.7M $15.4M spent |
| Grant Road Segment 4 - from Cypress Rose Hill Road to Telge Road - 2018 20104MF1BM01 · Precinct 3 · county record |
Active Design finish 2028-05-02 |
$15.5M $1.9M spent |
| Hufsmith-Kohrville Road Segment 4 - from 500' north of Holderreith Road to Mahaffey Road - 2015 15104M23NP04 · Precinct 3 · county record |
Active Study finish 2034-03-29 |
$14.8M $720.2K spent |
| Boudreaux Road Segment 3 - from Old Boudreaux Road to 300' west of Hufsmith-Kohrville Road - 2019 20104MF1C401 · Precinct 3 · county record |
Active Design finish 2032-01-11 |
$14.5M $1.5M spent |
| North Eldridge Parkway - from Spring Cypress Road to Gregson Road - 2015 15104MF0D701 · Precinct 3 · county record |
Active Bid finish 2029-12-12 |
$13.6M $3.1M spent |
| Road Improvements - Garth Rd 1 FM 1942 to South of Sterling Summer Dr - 2024 24103MF3G901 · Precinct 3 · county record |
Active Study finish 2032-04-16 |
$13.3M $219.1K spent |
| Will Clayton Pkwy Segment 1 - from 2,700-ft West of South Houston Ave to 1,370-ft East of Wilson Rd - 2022 23103MF2WB01 · Precinct 3 · county record |
Active Design finish 2027-08-06 |
$13M $667K spent |
| Porter Rd - Clay Rd to Stockdick School Rd - 2023 24104MF3A301 · Precinct 4 · county record |
Active Design finish 2030-10-31 |
$12.9M $344.6K spent |
| Roadway Maintenance - Asphalt Rehabilitation Package - 2 - 2026 25103MF3PK01 · Precinct 3 · county record |
Active Bid finish 2028-11-06 |
$12.9M $0 spent |
| Hike and Bike Trail - SCG - Gosling Road to Dr. Ann Snyder Way - 2022 22104MF03R01 · Precinct 3 · county record |
Active Study finish 2027-11-09 |
$12.3M $566.8K spent |
| Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019 20104MF1C801 · Precinct 3 · county record |
Active Design finish 2029-04-04 |
$12.1M $627.8K spent |
| Road Improvements - Garth Rd 2 South of Sterling Summer Dr to Ashbel Cove Dr - 2024 24103MF3GA01 · Precinct 3 · county record |
Active Study finish 2032-04-14 |
$11.3M $497.5K spent |
| Holderrieth Rd Segment 3 - from Hufsmith-Kohrville Rd to Sir Alex Dr - 2017 18104MF0RA01 · Precinct 3 · county record |
Active Design finish 2030-11-07 |
$11.1M $2.3M spent |
| Boudreaux Road Segment 4 - from 200' east of Hufsmith-Kohrville Road to 700' south of SH-99 - 2022 23103MF2P601 · Precinct 3 · county record |
Active Design finish 2032-08-04 |
$10.9M $336.8K spent |
| Hufsmith-Kohrville Road Segment 3B - from 400' north of Boudreaux Road to 600' north of Holderrieth Road - 2015 23103MF2Q701 · Precinct 3 · county record |
Active Design finish 2032-02-10 |
$10.4M $241.5K spent |
| Mueschke 9; 500' north of Draper Road to approximately 1000' north of FM 2920 171033020712 · Precinct 4 · county record |
Active Design finish 2029-06-13 |
$10.2M $2.6M spent |
| University Asia Town Multimodal Path - 2024 24104MF3BJ01 · Precinct 4 · county record |
Active Initiation finish 2028-12-16 |
$10.2M $166.5K spent |
| Roadway Maintenance - Asphalt Rehabilitation Package - 1 - 2026 25103MF3PJ01 · Precinct 3 · county record |
Active Bid finish 2028-08-14 |
$9.1M $482.3K spent |
| Grant Road Segment 3 - from Telge Rd to Shaw Rd - 2018 19104MF10501 · Precinct 3 · county record |
Active Design finish 2029-03-12 |
$9M $811.7K spent |
| West Rayford Rd Segment 1 - from Kuykendahl Rd to 400' east of W Augusta Pines Pkwy - 2019 20104MF1BT01 · Precinct 3 · county record |
Active Study finish 2027-06-04 |
$8.9M $740.1K spent |
| South Diamondhead Blvd - from 500-ft West of Sea Palms Dr. to West of Boom Dr. - 2022 23103MF2QZ01 · Precinct 3 · county record |
Active Study finish 2031-06-27 |
$8.9M $358.9K spent |
| Corridor Study - Mason Road - 2025 25104MF3WR01 · Precinct 4 · county record |
Active Planning finish 2027-02-03 |
$7.8M $0 spent |
| Memorial Parkway Subdivision Drainage Improvements - 2018 19103MF14E01 · Precinct 4 · county record |
Active Design finish 2029-01-18 |
$7.3M $950.7K spent |
| North Eldridge Parkway - from South of Pine Drive to South of Lakewood Meadow Drive - 2021 22103N306630001 · Precinct 3 · county record |
Active Construction finish 2027-05-15 |
$6.2M $1.4M spent |
| Hike and Bike Trail - Faulkey Gully - K142-00-00 - 2022 23103MF2W701 · Precinct 3 · county record |
Active Construction finish 2029-03-07 |
$5.8M $2.7M spent |
| Detention Basin Enhancement Program - Goforth - 2021 21103N306330001 · Precinct 3 · county record |
Active Warranty finish 2027-03-20 |
$5.3M $5M spent |
| Asphalt Reconstruction Project - Fuqua St.: Furman Rd. to Cullen Blvd. - 2022 22101MF2HR01 · Precinct 1 · county record |
Active Bid finish 2028-07-15 |
$5.1M $268.3K spent |
| Birnam Wood Blvd Segment 1 - from 450' north of Hickorygate Dr to south of J109-01-01 - 2019 20104MF1BG01 · Precinct 3 · county record |
Active Bid finish 2028-12-29 |
$5M $632.5K spent |
| 15530 Huffmeister Road (Cypress Camp) - Expansion - 2024 24103MF3EX01 · Precinct 3 · county record |
On-Hold Planning finish 2028-08-30 |
$4.6M $102K spent |
| Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024 25103MF3MT01 · Precinct 3 · county record |
Active Warranty finish 2027-06-24 |
$4.2M $2.3M spent |
| Precinct 1 Facility Improvements - 2700 El Camino Street parking- 2025 25101MF3S501 · Precinct 1 · county record |
Active Construction finish 2028-06-29 |
$3.2M $317.7K spent |
| Subdivision Reconstruction - Patiowoods - 2024 24208MF3FA01 · Precinct 3 · county record |
Active Design finish 2029-03-12 |
$3.2M $379.3K spent |
| Subdivision Drainage Improvements - Lakeshore - 2024 24103MF3HD01 · Precinct 3 · county record |
Active Construction finish 2027-12-06 |
$2.6M $403.3K spent |
| Sidewalk - South Mason from Kingsland Blvd to County Line - 2023 24104MF38501 · Precinct 4 · county record |
Active Construction finish 2028-03-07 |
$2.6M $317.6K spent |
| Sidewalk - Energy Corridor and MultiModal Connectivity - Precinct 4 - 2023 24104MF38Q01 · Precinct 4 · county record |
Active Study finish 2030-02-07 |
$2.4M $440.7K spent |
| Subdivision Reconstruction - Mobile Homes Parkland - 2024 24208MF3FC01 · Precinct 3 · county record |
Active Study finish 2027-12-20 |
$2.1M $296.6K spent |
| Drainage Improvements - Huffman Cleveland Road 2024 24103MF3G801 · Precinct 3 · county record |
Active Study finish 2028-01-19 |
$1.9M $194.1K spent |
| Traffic Signal - City of Piney Point Phase 1 - 2022 23103MF2V801 · Precinct 3 · county record |
Active Construction finish 2028-04-25 |
$1.8M $263.3K spent |
| Geotechnical Investigation - Precinct 1 Infrastructure Revitalization Program - Packages 2-6 - 2026 2610135JXB01 · Precinct 1 · county record |
Active Study finish 2026-11-23 |
$1.4M $0 spent |
| Corridor Study - Clinton Drive - 2024 24102MF3K301 · Precinct 2 · county record |
Active Planning finish 2027-01-29 |
$1.2M $95.9K spent |
| Subdivision Improvements - Arcadian Gardens Phase 1 - 2024 24103MF3E801 · Precinct 3 · county record |
Active Study finish 2029-12-04 |
$925.5K $449K spent |
| Sidewalk - Ella Boulevard / Falvel Road - 2022 23103MF2UF01 · Precinct 3 · county record |
Active Warranty finish 2026-01-07 |
$907.3K $107.1K spent |
| Corridor Study - Reimagine Hopper Rd - 2024 24102MF3JX01 · Precinct 2 · county record |
Active Planning finish 2026-06-23 |
$628.9K $431.1K spent |
| Lift Station Wet Well Rehabilitation - Tom Bass and Adair Parks - 2024 25101MF3Q601 · Precinct 1 · county record |
Active Warranty finish 2026-09-15 |
$282.2K $278K spent |
| Sidewalk - Royalwood Drive - 2024 25102MF3NS01 · Precinct 2 · county record |
Active Warranty finish 2027-03-11 |
$184.3K $178.2K spent |
| Bridge Repair - Ella Blvd Over Seals Gully, Precinct 3 24103MF34001 · Precinct 3 · county record |
Active Design finish 2028-08-04 |
$160K $11.3K spent |
| Cutten Rd - from south of Bavaria Dr to Cossey Rd - Phase II - 2026 20104MF1C802 · Precinct 3 · county record |
Active Design finish 2028-02-04 |
$0 spent |
| Bridge Repairs - BRINSAP Package 1 - 2027 261030AU4C01 · Precinct 3 · county record |
Active Scoping finish 2028-04-09 |
$0 spent |
| Roadway Maintenance - Residential Asphalt Package Crosby - 2027 26103YI64C01 · Precinct 3 · county record |
Active Planning finish 2028-04-09 |
$0 spent |
| Roadway Maintenance - Asphalt Package Cypress North Houston - 2027 26103ZE04C01 · Precinct 3 · county record |
Active Scoping finish 2026-08-14 |
$0 spent |
Sources
- Harris County Engineering Department, bond project map (CIPBondMapping)
- Harris County Flood Control District, 2018 Bond Program project table (posted by ReduceFlooding.com, from Commissioner Ramsey's office; the newest quarter is found automatically) · HCFCD 2018 Bond Program
- City of Houston, Capital Improvement Plan projects by council district